Reconciling hours, cycles and LLP life before an aircraft lease return
Return conditions and compensation are written in hours, cycles and remaining life of life-limited parts. Before the lessor reviews those figures, make sure your own records agree with each other and project them to the return date.
Why the figures must agree
The same counters appear in many documents: utilisation reports, engine status reports, LLP status sheets, shop visit reports and logbooks. When two of them disagree, the lessor's technical representative will ask which one is right, and the answer can take days to establish once the records review has started.
Reviewing the figures against each other before the lessor does turns those queries into corrections made on your own schedule.
What a lessor usually looks for
- Totals since new for the airframe and each engine, APU and landing gear, consistent from one dated document to the next.
- Life-limited part figures that are consistent with the cycles each part has flown.
- Counters since the last shop visit or overhaul that are consistent with the visit records.
- Serial numbers that match the installations and removals recorded during the lease.
- Status documents that are dated, signed and traceable to their source.
Organise the figures before reviewing them
- Keep one series per serial number and per counter. Two engines that took turns at one position are two units, not one series.
- Date every figure with the date it is given at, not the date the document was received.
- When a document corrects an earlier one, keep both and record which one replaces which; never let a later entry silently erase an earlier one.
- Keep the source of every figure: the document, its revision and the page.
- Set aside figures without a date or a serial number until they are completed: they cannot be placed in a series.
Project the figures to the return date
A return condition applies on the return date, so project each unit's latest figure to it at the planned utilisation: totals grow, remaining life shrinks. State the utilisation you used and its date, because the projection moves with it.
Fictional example: an engine's most limiting LLP has 3,766 cycles remaining on 30 September 2026. At 150 cycles a month, about 833 cycles are flown by a return on 18 March 2027, leaving about 2,933, which is 67 short of a condition of at least 3,000. At that utilisation the limit is reached around 4 March 2027, 14 days before the return: early enough to plan a replacement or to agree compensation, too late to discover at the records review.
A projection is an estimate, not a finding: treat a projected shortfall as a planning decision and keep the figures, the utilisation and the date it was made with it.
When two records disagree
- Go back to the source documents of both figures before changing anything.
- Correct the wrong figure with a sourced record rather than editing the old one, and keep both.
- Never set aside a doubt about a life-limited part without a sourced record that resolves it, such as the part replacement or the revised limit.
- Log what cannot be resolved at once as an open item with an owner, a due date and the evidence that will close it.
- Tell the lessor early about a discrepancy you have found and how you will resolve it; it costs far less than one they find.
Enter the return date, the monthly utilisation and each counter's latest value: the tracker projects it to the return date and shows the margin, the result and the day the limit is reached. Six worked, fictional rows.
Download the Excel templateSources and scope
Prepared by Redelvia. These references cover the industry and regulatory context. The workflow examples are our own illustrations; your lease and the applicable authority determine the requirements for your aircraft.
- EASA — Continuing Airworthiness: technical records FAQs
Explains continuing airworthiness records and distinguishes regulatory record requirements from the industry term back-to-birth.
- IATA — Aircraft Leasing Policy & Standards
Access to IATA's aircraft lease guidance, including delivery and redelivery preparation. Use the agreed lease to establish the conditions for your aircraft.